Checklist for Inspection and Maintenance

The following checklists contain all regular inspection and maintenance work in tabular form. Each line describes a maintenance item using the following information:

  • Interval
  • Assembly
  • Action
  • Reference to the chapter where the activity is described in detail

The interval column is sub-divided into Categories A, B and C.

  1. Interval in operating time of the machine
  2. Interval in realtime, independent of the running time of the machine
  3. Maintenance work as indicated on the machine's main operator panel

Double detail under A and B mean: This work must be carried out after operating time A or realtime B, whichever occurs earlier.

Abbreviation for time units:

  1. Hours
  2. Days
  3. Weeks
  4. Months
  5. Years

After intervals of 8, 50, 200 etc. hours have lapsed, follow the checklist in Section 3.2. You can carry out this work during production.

The checklist is spilt into intervals, starting with the shortest operating time interval (8 hours). Complete all work from the first to the last line of the due interval.

Example: After 200 operating hours, complete all work for 8, 50, and 200 hour intervals